Villa Bergström - a dream project

 

  

Tuesday w.26. Yesterday the outline of the outer wall of the garage were build. To day the sill for the outer walls were in place. Tomorrow the first wall will be raised.

 

 

Wednesday w.26 The first, second, third... wall is up. Everything´s movin in an incredible pace rightnow.

 

 

Thursday w.26 The picture is from lunchtime. Before the day was over all the outer walls were up, along with the inner wall towards the childrens rooms. It´s unbelievable but tomorrow the roof truss will be set in place. It´s starting to look like a house. A big beautifull house... This evening we even did the first house cleaning.

 

 

Friday w.26 The builders have made an incredible job this week. They have even worked late nights to get the roof truss in place. Now you can really see the shape of the house.

 

Monday w.27 The roof is starting to be covered.

 

Tuesday w.27  Roof on the southeast side of our house. The builders has a tight schedule to get the house totally covered to the end of the week.

 

End w.27  A well covered house. The construction workers has now started a well deserved holiday.

 

  

Inside pictures from our future living room. The little pipe in the floor marks the fire place.

Sunday w27:  A very hot day and here is the house from the entreance side. We now have four weeks to do the finishing touches on the constuktion. Fasten bouth sides of the roof truss, outer 7 cm insulation and the lath for the roof tiles.

 

Tuesday w. 28 Peter and his father have finished the vertical lath, now there is only the horisonal left to do.

 

w. 37 The roof tiles

 

w.40 Rooftiles are in place.

 

w.42

 

w. 43 monday

 